It's Friday! Remember that poll I sent out earlier this week about whether you wanted to see me do a meeting recap video series? Well, I made a rough cut and wanted to show you all. This one breaks down the Fort Pierce city attorney situation and Project Orchid all in one go. These do take a lot to produce, so they'll eventually be for Patreon and People Pass members only, but I'm sharing this one broad to get your thoughts. Check it out here.
💜 People Pass Shoutout: Thank you to everyone supporting the newsletter! If you want to help keep this going, support here.
In today's newsletter:
🏗️ A data center campus is quietly moving through the City of Fort Pierce
💧 Vero Beach water rates rise over four years, combined bill reaching $122 by 2030
🗑️ Port St. Lucie returns $24 million trash settlement to property owners
💻 Martin County commissioners consider data center moratorium following community concerns
⛈️ Weather Update: Shifting clouds and sun with thunderstorms, humid all day.
☀️ Day: High of 92°F | Couple of thunderstorms, 88% chance of rain.
🌙 Night: Low of 75°F | Partly cloudy and humid, a couple of showers late.
🌅 Sunrise: 6:58 AM | 🌇 Sunset: 7:47 PM
🌙 Moonrise: 8:07 PM | 🌚 Moonset: 8:15 AM
🎶 Sounds like: "All Night" — Chance the Rapper ft. Knox Fortune
Ja'Min Devon
Founder & Publisher, Sunland News
🟠 Main Squeeze: A data center campus is quietly moving through the City of Fort Pierce

Remember that wave pool project everyone was talking about? That was the last big proposal for this land. Now there is data center being proposed on the same land. Here is the quick video breakdown 🏗️.
A company called Willow Lakes LLC owns approximately 200 acres at the northwest corner of I-95 and West Midway Road in Fort Pierce. The developer is Devcon Digital, which is calling the project Project Neptune. They have filed a rezoning application with the City of Fort Pierce.
What is being proposed 📋:
🏢 174 acres rezoned to Light Industrial, restricted by a 50 year covenant to data center use only
🛍️ 26 acres along West Midway Road rezoned to General Commercial for retail, a hotel, gas station or restaurants
⚡ Full build out capacity projected at over one gigawatt of dedicated computing power
Why this site: The property already has two FPL high voltage transmission easements crossing it and a major substation sitting directly south. A large man made lake already on site is intended for cooling instead of municipal drinking water. Direct I-95 access means traffic does not route through residential streets.
How this process works: Technical Review Committee heard this on August 20th. Next is the Planning and Zoning Board, then the Fort Pierce City Commission. Residents can weigh in at both the Planning and Zoning meeting and at the City Commission meeting. The full application record is public and includes a traffic impact analysis, environmental assessment and drainage analysis. The developer also maintains a public knowledge center with answers to common questions.
What's next: Planning and Zoning Board date has not yet been noticed. We will be following this closely 📅.
📰 Press Round: Rates, Refunds & Regulations

💧 Vero Beach Water Rates Rise Over Four Years
Vero Beach City Council unanimously approved phased water and sewer rate increases beginning October. The combined bill will rise from $83.54 to $122 by 2030, adding about $11.38 monthly. Wastewater rates increase 15% annually for two years, then 10% and 5%. Water rates rise 10%, 7.5%, 5% and 5%. The increases fund $217 million in capital improvements including a new wastewater treatment facility to replace the 50-year-old plant.
👉 Read more (WQCS)
🗑️ Port St. Lucie Returns $24 Million Trash Settlement
Port St. Lucie property owners will receive credits on their 2026-2027 solid waste fees from a $24 million lawsuit settlement with Waste Pro over the 2021 garbage crisis. Residents who owned homes since 2022 get $364 credits; newer residents receive $64. The $482.16 solid waste fee becomes $118.16 for long-term owners. Those who moved between city homes can claim the full $364 through February 20.
👉 Read more (TCPalm subscription may be required)
💻 Martin County Commissioners Consider Data Center Pause
Martin County commissioners voted 4-1 to discuss a possible data center moratorium at their next meeting following community concerns about hyperscale facilities. Residents worry about impacts on air quality, noise, water usage and electrical infrastructure. The proposed one-year pause would give commissioners time to develop regulations. County staff will present information about the county's authority under state laws SB 180 and SB 484.
👉 Read more (WPTV)
📖 Thanks For Reading: How was today’s newsletter?
👋 Thanks for reading! If you found it useful, consider sharing it with a friend.
📱 Keep up with the Sunland News: Send comments & suggestions to [email protected] Follow us on, Instagram, Facebook, and Youtube
🙋♂️ Did someone forward you this? Subscribe Below!